Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget. Based on the average velocity of a previous product release, Paul had estimated a new product to take 9 Sprints to complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not fully completing the required integration tests. The Development Team estimates that integration testing would require additional effort to make the increments shippable. The
Development Team is unsure if the required velocity is achievable.
What is the most effective way to recover?
Mbouzidi
5 months agoMi_Windsor
7 months, 2 weeks agoPaulWaltR
1 year agoHana9
1 year, 7 months agoamog
3 years, 9 months ago