Steven is a Scrum Master for three different teams building a single product from the same Product Backlog. Development Team members from each team have approached Steven complaining that their teams need Nicole, an external specialist, to commit full time for their next Sprint.
Which three acceptable solutions would Steven consider? (Choose three.)