Which two ways of creating Development Teams are consistent with Scrum's values? (Choose two.)

  • A. Existing teams propose how they would like to go about organizing into the new structure.
  • B. Managers personally re-assign current subordinates to new teams.
  • C. Managers collaborate to assign individuals to specific teams.
  • D. Bring all the developers together and let them self-organize into Development Teams.
  • E. The Chief Product Owner determines the new team structures and assignments.
Show Suggested Answer Hide Answer
Suggested Answer: AD 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jyoti1010
1 year, 2 months ago
Selected Answer: AD
A and D
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
A and D are correct
upvoted 1 times
...
mgharably
2 years, 7 months ago
Selected Answer: AD
Answet is A D
upvoted 1 times
...
SamuelZhang
3 years, 7 months ago
There are no managers in scrum
upvoted 1 times
...
buxi_eu
3 years, 9 months ago
Why not CE?
upvoted 1 times
JoshyKawasaki
1 year, 5 months ago
Not C - There are no managers in Scrum Framework Not E - Scrum focus is on self-management; decision is ultimately with the Dev Team.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...