The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)
A.
Inform the Product Owner's functional manager.
B.
Stop the Sprint, send the Product Owner to a course and restart.
C.
Bring up the problem in the Sprint Retrospective.
D.
Coach the Product Owner in the values of Scrum and incremental delivery.