Exam PSM I topic 1 question 61 discussion

Actual exam question from Scrum's PSM I
Question #: 61
Topic #: 1
[All PSM I Questions]

The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)

  • A. Inform the Product Owner's functional manager.
  • B. Stop the Sprint, send the Product Owner to a course and restart.
  • C. Bring up the problem in the Sprint Retrospective.
  • D. Coach the Product Owner in the values of Scrum and incremental delivery.
  • E. Nominate a proxy Product Owner.
Show Suggested Answer Hide Answer
Suggested Answer: CD 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
amog
Highly Voted 3 years, 9 months ago
C and D are correct
upvoted 6 times
...
Jyoti1010
Most Recent 1 year, 2 months ago
Selected Answer: CD
Correct C and D
upvoted 1 times
...
reika1914
1 year, 3 months ago
Selected Answer: CD
C and D are correct
upvoted 1 times
...
itzOG_
2 years, 7 months ago
Yes C & D is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...