Which of the following are true about the length of the Sprint? (Choose two.)
A.
The length of the Sprint should be proportional to the work that is done in between Sprints.
B.
It is best to have Sprints of consistent length throughout a development effort.
C.
Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing.
D.
Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.
B and E
The heart of Scrum is a Sprint, a time-box of one month or less during which a ‘Done’, useable, and potentially releasable product Increment is created.
Les énoncés vrais concernant la durée du sprint sont :
B. Il est préférable d'avoir des sprints d'une durée constante tout au long d'un effort de développement.
D. La durée du sprint est déterminée lors de la planification du sprint et doit être suffisamment longue pour garantir que l'équipe de développement peut livrer ce qui doit être accompli lors du prochain sprint.
B. Il est préférable d'avoir des sprints d'une durée constante tout au long d'un effort de développement.
D. La durée du sprint est déterminée lors de la planification du sprint et doit être suffisamment longue pour s'assurer que l'équipe de développement peut livrer ce qui doit être accompli dans le sprint à venir.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
hiepnb97
8 months, 3 weeks agoJyoti1010
1 year, 2 months agoAlbinopreto
1 year, 3 months agovasco999
1 year, 3 months agoMi_Windsor
1 year, 3 months agoAlbinopreto
1 year, 3 months agoamog
3 years, 9 months ago