Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PSM II All Questions

View all questions & answers for the PSM II exam

Exam PSM II topic 1 question 50 discussion

Actual exam question from Scrum's PSM II
Question #: 50
Topic #: 1
[All PSM II Questions]

A new Product Owner has joined an existing Scrum Team that has been working together for eight Sprints. The Development Team has grown to have a good understanding of the functionality and business for the product they have been building. The Product Owner, being new to the company, is unsure about his responsibilities.
As a Scrum Master explain what two acceptable ways of helping the Product Owner would be. (Choose two.)

  • A. You advise the Product Owner to start building a good relationship with the stakeholders of the product. Ongoing interaction with them is important to regularly align with changing organizational or market expectations. The Product Owner is also expected to invite the right stakeholders to the Sprint Review meeting.
  • B. You inform the Product Owner that, in today's highly competitive markets, it is important that the Development Team is updated on changing business priorities on a daily basis. The Daily Scrum allows the Development Team to adapt to the changes in scope without delay.
  • C. You tell the Product Owner to make sure that there are no ambiguities or possible misunderstandings in the items on the Product Backlog when they are handed over to the Development Team. This is best done by capturing the functional requirements during an analysis phase, resulting in documents that are considered as the working product of such analysis Sprints.
  • D. You advise the Product Owner to rely on the Development Team and the stakeholders to formulate the Product Backlog, as they are the ones most knowledgeable. By asking questions and working with them the Product Owner will quickly be up to speed.
Show Suggested Answer Hide Answer
Suggested Answer: AD 🗳️
The ones that are closest to the work are the best ones to understand and explain what the work is and what the needs of the users and product are.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mbouzidi
4 months ago
Selected Answer: AD
A D are correct
upvoted 1 times
...
ferut
1 year, 5 months ago
C is incorrect, no such thing as 'Analysis Sprints'
upvoted 1 times
...
supera123
1 year, 5 months ago
A and B
upvoted 1 times
...
nhungnt184
3 years, 7 months ago
C is wrong because there is no analysis Sprints. A is correct. I am not sure about the remaining options.
upvoted 1 times
...
amog
3 years, 8 months ago
As Scrum Master, you can't tell PO to do something. Also there are no analysis Sprints Answer is A and D
upvoted 2 times
lenanguyen89
1 year, 5 months ago
Why it is not B?
upvoted 1 times
MikeSmuts
5 months, 1 week ago
Because the Daily Scrum is meant for the Dev Team, not the PO or SM.
upvoted 1 times
...
...
...
Elaine520
3 years, 8 months ago
agreed with AC
upvoted 2 times
AVK
3 years, 8 months ago
SM will oly facilitate nd be a helping hand not a driving force for product owner. so A nd D answer
upvoted 1 times
...
...
Edgecrusher77
3 years, 9 months ago
Not agree, I would say A & C
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...