By the end of the Sprint, a Product Backlog item in the Sprint Backlog does not meet the team's Definition of Done. What two things should happen with the item? (Choose two.)
A.
It will be inspected at the Sprint Review and if it is acceptable by the stakeholders then include it in the Increment.
B.
Do not include the item in the Increment for the Sprint.
C.
Split the item and add the estimation of the completed work to the current Sprint so not to impact the velocity and add the 'undone' work to the next Sprint.
D.
Estimate the remaining work needed to make it 'done' and add it to the Product Backlog for the Product Owner to decide what to do with it.
Suggested Answer:BD🗳️
At the end of a Sprint, the new Increment must be 'Done', which means it must be in useable condition and meet the Scrum Team's definition of 'Done'. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the Definition of Done for the Scrum Team and it is used to assess when work is complete on the product Increment.
Not sure about this one, should be A & D.
If it's accepted by stakeholder, it can be accepeted in the increment, they are the one judging the end product.
As the item is not meeting DoD so it cant be considered for increment. And i feel it should be shown to the stakeholder too.
upvoted 1 times
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Mi_Windsor
1 year, 4 months agoamog
3 years, 8 months agoEdgecrusher77
3 years, 9 months agoAVK
3 years, 8 months ago