How much of the Sprint Backlog must be defined during the Sprint Planning event?

  • A. Just enough tasks for the Scrum Master to be confident in the Development Team's understanding of the Sprint.
  • B. The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
  • C. Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
  • D. Just enough to understand design and architectural implications.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Gusthwolf
Highly Voted 2 years, 2 months ago
Scrum Guide says “The Sprint Goal must be finalized prior to the end of Sprint Planning” NOT the Sprint Backlog. Sprint Backlog can be updated anytime during the Sprint by the Development Team, keeping the Sprint Goal unchanged.
upvoted 9 times
mgharably
1 year, 2 months ago
Totally agree with you
upvoted 1 times
...
...
NavneetK
Highly Voted 2 years, 5 months ago
its not B, as spring backlog keeps evolving during the sprint, it can not be estimated entirely in scrum planning. C is correct.
upvoted 8 times
...
julioglez88
Most Recent 1 month ago
Selected Answer: C
The correct answer is C. Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint. The Sprint Backlog is a plan by and for the Developers. It is a highly visible, real-time picture of the work that the Developers plan to accomplish during the Sprint in order to achieve the Sprint Goal. The Sprint Backlog is created during the Sprint Planning event and then added to throughout the Sprint as new work is identified. The Sprint Backlog is owned by the Developers, and they are responsible for updating it and keeping it accurate. The Sprint Backlog should be detailed enough so that the Developers can create their best forecast of what they can do during the Sprint, and to start the first several days of the Sprint. However, it does not need to be complete, and it can be updated throughout the Sprint as new work is identified
upvoted 2 times
...
NavneetK
2 years, 5 months ago
its not B, as sprint backlog keeps evolving during the sprint, it can not be estimated entirely in scrum planning. C is correct.
upvoted 4 times
...
Mrtn_Fgra
2 years, 5 months ago
I think the answer is B
upvoted 1 times
...
FullSoftwares
2 years, 6 months ago
Should the correct answer be B?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago