Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 140 discussion

Actual exam question from Scrum's PSM I
Question #: 140
Topic #: 1
[All PSM I Questions]

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

  • A. It is a complete list of all work to be done in a Sprint.
  • B. Every item has a designated owner.
  • C. Each task is estimated in hours.
  • D. It is the Scrum Team's plan for the Sprint.
  • E. It is ordered by the Product Owner.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sam_69
Highly Voted 3 years, 11 months ago
Correct answer is D. I had it for the official test
upvoted 14 times
...
ThomasBac
Highly Voted 3 years, 11 months ago
I think the correct answer is D. The Sprint Backlog must not be fully completed after Sprint Planning.
upvoted 14 times
...
rspl382
Most Recent 11 months ago
While option A is partially correct in that the Sprint Backlog does represent the work to be done in a Sprint, it doesn't capture the collaborative and dynamic nature of the Sprint Backlog. The Sprint Backlog is not a static, exhaustive list created solely by the Product Owner; instead, it's a dynamic plan developed by the Scrum Team during Sprint Planning. Option D, "It is the Scrum Team's plan for the Sprint," better emphasizes the collaborative effort of the Scrum Team in creating and owning the Sprint Backlog. It reflects the idea that the team collectively decides on the work to be undertaken during the Sprint and how it will be accomplished.
upvoted 1 times
...
emelba
11 months, 1 week ago
D. Answer A, "It is a complete list of all work to be done in a Sprint," is not the best choice because the Sprint Backlog is not intended to be a comprehensive and exhaustive list of all the work to be done in a Sprint at the beginning. Instead, it is a living document that evolves throughout the Sprint.
upvoted 1 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: D
Correct answer is D.
upvoted 2 times
...
alexseles
1 year, 1 month ago
Selected Answer: D
D. É o plano do Time Scrum para o Sprint. O Sprint Backlog é uma lista de itens do Product Backlog selecionados para o Sprint e a meta do Sprint. Ele é uma parte do plano geral do Sprint, detalhando o trabalho que a equipe se compromete a realizar durante o Sprint. Portanto, a opção D é a mais precisa em relação ao Sprint Backlog.
upvoted 1 times
...
alexseles
1 year, 1 month ago
D. É o plano do Time Scrum para o Sprint. O Sprint Backlog é uma lista de itens do Product Backlog selecionados para o Sprint e a meta do Sprint. Ele é uma parte do plano geral do Sprint, detalhando o trabalho que a equipe se compromete a realizar durante o Sprint. Portanto, a opção D é a mais precisa em relação ao Sprint Backlog.
upvoted 1 times
...
UppersquareCapital
1 year, 2 months ago
The correct answer is A. Although I understand why most people here think it is D. Firstly, according to the scrum guide, "The sprint Backlog is a plan by and for the Developers". However, option D refers to the Sprint Backlog as the Scrum Team's plan. The sprint is owned by the Developers and not the Scrum Team. The Scrum Guide further say ... the Sprint Backlog is a real-time picture of the work that the Developers plan to accomplish during the Sprint in order to achieve the Sprint Goal.
upvoted 1 times
...
reika1914
1 year, 4 months ago
Selected Answer: D
Correct answer is D
upvoted 2 times
...
EgycrmDev
2 years, 7 months ago
Selected Answer: D
the Sprint Backlog is not a complete list as the work keeps emerging as they know more
upvoted 2 times
...
SterG
3 years, 8 months ago
I would say D, as the Sprint Backlog is not a complete list as the work keeps emerging as they know more.
upvoted 5 times
EgycrmDev
2 years, 7 months ago
Agree with you
upvoted 1 times
...
...
amog
3 years, 9 months ago
Answer is D
upvoted 2 times
...
lohlah_
3 years, 10 months ago
D - because According to the scrum guide 2020- the sprint backlog is composed of the sprint goal (why), the set of product backlog items selected for the sprint (what) as well as the actionable plan for delivering an increment (how)
upvoted 6 times
lohlah_
3 years, 10 months ago
+++++ also according to the scrum guide 2020 - the sprint backlog is a plan by and for the developers.
upvoted 3 times
...
...
Arend78
3 years, 10 months ago
A backlog item is a plan, the tasks in it the work. During a sprint, more clarity can arise around the work needed
upvoted 2 times
...
kienbt241090
3 years, 10 months ago
A. Sprint Blacklog contains plan, not a plan.
upvoted 2 times
...
Edgecrusher77
3 years, 11 months ago
Yes I think it's D. Sprint Backlog is not always fully completed after Sprint Planning
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...