The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)
A.
Opportunities to inspect and adapt the Sprint Backlog are lost.
B.
Impediments are raised and resolved more slowly.
C.
The Product Owner cannot accurately report progress to the stakeholders.
D.
Too much work is spent updating the Scrum board before the meeting.
E.
The Scrum Master loses the ability to update the Gantt chart properly.
If the impediment are raised and resolves slowly (option B) that sprint plan to achieve sprint goal will become inaccurate (Option F). So option A,B and F are correct in my opinion.
PO and SM do not partecipate to the Daily Scrum unless they partecipate as developers
upvoted 5 times
...
...
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sujo
Highly Voted 3 years, 8 months agoermat
Most Recent 3 months, 1 week agoJyoti1010
1 year, 2 months agoJyoti1010
1 year, 2 months agodandirindan
2 years, 7 months agoEdgecrusher77
3 years, 11 months agokalguthor
3 years, 11 months agoPancogito
3 years, 11 months agoTianee
3 years, 7 months agoaam1972
2 years, 7 months ago