When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

  • A. The Development Team.
  • B. The Product Owner and all stakeholders.
  • C. The Product Owner and the Development Team.
  • D. The Scrum Master, project manager and Development Team.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sam_69
Highly Voted 3 years, 11 months ago
i had the question "When a Development Team determines that it has over-committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected?" and the right answer is PO + Dev Team
upvoted 17 times
3434343
3 years, 11 months ago
You had it on PSM1 exam? And had exact words "who has to be present" instead "should be present"?!
upvoted 2 times
Devornasa
3 years, 10 months ago
IHe is correct, it should be PO + Dev
upvoted 3 times
...
...
emelba
10 months, 3 weeks ago
If you already took the exam, what are you doing here?
upvoted 1 times
...
...
Giangio
Highly Voted 3 years, 11 months ago
The answer is C
upvoted 7 times
...
MarcoScaramelli
Most Recent 9 months, 1 week ago
Answer C is correct
upvoted 1 times
...
6fcf1a4
11 months, 1 week ago
According to ChatGPT, "While not mandatory, it can be beneficial to involve the Product Owner in the discussion"
upvoted 1 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: C
Scope renegotiation always occurs in the presence of PO and developers.
upvoted 2 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: C
PO and Development team.
upvoted 1 times
...
Rollizo
1 year, 2 months ago
Selected Answer: C
PO and DT analysing in sprint review together It is no talking about during a sprint
upvoted 1 times
...
Joshalom
2 years, 6 months ago
C is correct
upvoted 1 times
...
cap_examtopics
2 years, 7 months ago
Selected Answer: C
C is the correct answer on the open assessment.
upvoted 1 times
...
EgycrmDev
2 years, 7 months ago
Selected Answer: C
Answer is C
upvoted 1 times
...
sanaw12
3 years, 7 months ago
the answer is po+developers
upvoted 2 times
...
ptoul74
3 years, 8 months ago
Another extract from scrum.org open assessment quizz : During a Sprint, a Developer determines that the Scrum Team will not be able to complete the items in their forecast. Who should be present to review and adjust the Product Backlog items selected? (choose the best answer) Correct answer: D) A)The Developers. B) The Scrum Master, the project manager, and the Developers C) The Product Owner and all stakeholders. D) The Product Owner and the Developers.
upvoted 7 times
...
VoidedSun
3 years, 9 months ago
Correct answer should be C. Scrum guide: 1) "Only the Development Team can change its Sprint Backlog during the Sprint" 2) "If the work turns out to be different than the Development Team expected, they collaborate with the Product Owner to negotiate the scope of Sprint Backlog within the Sprint." 3) "The Product Owner can help to clarify the selected Product Backlog items and make trade-offs. If the Development Team determines it has too much or too little work, it may renegotiate the selected Product Backlog items with the Product Owner."
upvoted 5 times
...
reineflora
3 years, 10 months ago
exam topic, could you give us your opinion ?. from my point of view , the answer is C
upvoted 2 times
...
AminaL
3 years, 11 months ago
the answer is C
upvoted 1 times
...
sysop
3 years, 11 months ago
Don't be confused by another similar question. The answer for this one is A. This question asked "has to be present", thus, answer is A "Dev". Another question asked "should be present", thus, answer for that question is C "PO + Dev"
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...