Question #: 58
Topic #: 1
[All PSM I Questions]

The length of a Sprint should be:

  • A. Short enough to keep the business risk acceptable to the Product Owner.
  • B. Short enough to be able to synchronize the development work with other business events.
  • C. No more than one calendar month.
  • D. All of these answers are correct.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
okayhey
8 months ago
Selected Answer: D
D is correct
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
D is the correct answer
upvoted 1 times
...
Joshalom
2 years, 6 months ago
D is Correct
upvoted 1 times
...
abenomar
4 years ago
Correct answer is D. Sprints are limited to one calendar month (C). When a Sprint’s horizon is too long the definition of what is being built may change, complexity may rise (B), and risk may increase (A).
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...