exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 34 discussion

Actual exam question from Scrum's PSM I
Question #: 34
Topic #: 1
[All PSM I Questions]

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

  • A. The Scrum Team with the highest velocity pulls Product Backlog items first.
  • B. The Development Teams pull in work in agreement with the Product Owner.
  • C. The Product Owner should provide each team with its own Product Backlog.
  • D. Each Scrum Team takes an equal numbers of items.
  • E. The Product Owner decides.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
maverick_walker
2 months ago
B is correct
upvoted 1 times
...
Djedjig
4 months, 1 week ago
B is correct
upvoted 1 times
...
DipakKate
8 months ago
Option B
upvoted 1 times
...
Jyoti1010
9 months, 1 week ago
Selected Answer: B
Option B is correct.Developers in collaboration with product owner will decide.
upvoted 1 times
...
amit_swolf
10 months ago
Selected Answer: B
Single team or multiple, its development team responsibility to choose the work
upvoted 1 times
...
Mi_Windsor
10 months, 3 weeks ago
B is the correct answer
upvoted 1 times
...
VaheDA
3 years, 5 months ago
C is NOT the answer FOR SURE
upvoted 1 times
...
nhungnt184
3 years, 6 months ago
Cannot be C because there is only ONE product backlog in Scrum framework (even in Scrum of Scrums). B is the best option.
upvoted 3 times
...
Edgecrusher77
3 years, 6 months ago
It cant be C, only 1 Product backlog is possible per product. But you can have several Sprint backlogs, one per team. Correct answer is B
upvoted 3 times
...
babybaby
3 years, 7 months ago
The ansswer is B, 1 product= 1 product backlog=1 product owner
upvoted 3 times
...
Ansarfoolchand
3 years, 7 months ago
Ansar is C. Each team should have its own backlog.
upvoted 1 times
Mi001
3 years, 5 months ago
There is a single product backlog, I doubt you are right
upvoted 6 times
...
Tianee
3 years, 2 months ago
Team may have its own sprint backlog, but product backlog should always be just one.
upvoted 1 times
...
scrumk
3 years, 4 months ago
your answer is unethical in scrum as they must all have same product backlog
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago