Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

  • A. The Project Manager.
  • B. The Development Team.
  • C. The Scrum Team.
  • D. The Product Owner.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
lulux
Highly Voted 3 years, 8 months ago
Developers for new version Scrum Guide
upvoted 9 times
...
Djedjig
Most Recent 9 months, 1 week ago
B is correct
upvoted 1 times
...
kunlemaxwell
12 months ago
The answer is Developer, but the answers are not well worded. The Scrum Guide does not use the term "Development Team". Based on that, its confusing to want to pick Product Owner since they negotiate it with the Product Owner and the terminology is more consistent with the Scrum Guide.
upvoted 2 times
...
Mi_Windsor
1 year, 3 months ago
D - the developers
upvoted 1 times
...
Zuit
1 year, 4 months ago
Selected Answer: B
Sprint Backlog The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how). The Sprint Backlog is a plan by and for the Developers. It is a highly visible, real-time picture of the work that the Developers plan to accomplish during the Sprint in order to achieve the Sprint Goal. Consequently, the Sprint Backlog is updated throughout the Sprint as more is learned. It should have enough detail that they can inspect their progress in the Daily Scrum.
upvoted 2 times
...
julioglez88
1 year, 6 months ago
The development team determines when it is necessary to update the sprint backlog during the sprint. The development team may update the sprint backlog as needed to reflect changes in the project, the team's progress, or the team's understanding of the work. The development team should update the sprint backlog as soon as they become aware of any changes that may affect the sprint.
upvoted 3 times
...
Joshalom
2 years, 6 months ago
The Developers (SG2020)
upvoted 1 times
...
SGTAY
2 years, 7 months ago
Selected Answer: B
Developers for the 2020 version of Scrum Guide
upvoted 2 times
...
ZebraLynk
3 years, 7 months ago
B- L'équipe de développement est propriétaire du backlog Sprint.
upvoted 2 times
...
Naz1
3 years, 10 months ago
B - The Development Team.
upvoted 3 times
...
dcturra
4 years, 2 months ago
The develop team is the owner of the Sprint backlog.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...