A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items `Done` by the end of the Sprint. Which three phrases best describe the purpose of a definition of `Done`? (Choose three.)
A.
It controls whether the developers have performed their tasks.
B.
It provides a template for elements that need to be included in the technical documentation.
C.
It creates transparency over the work inspected at the Sprint Review.
D.
It trucks the percent completeness of a Product Backlog item.
E.
It guides the Development Team is creating a forecast at the Sprint Planning.
F.
It defines what it takes for an Increment to be ready for release.
It is C E F --> E because in the Scrum Guide it says: The same definition guides the Development Team in knowing how many Product Backlog items
it can select during a Sprint Planning.
CEF
Options A, B, and D do not accurately describe the purpose of a Definition of Done. It is not about controlling whether developers have performed their tasks, providing a template for technical documentation, or tracking the percentage completeness of a Product Backlog item.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
borabora
Highly Voted 5 years agoarualpcl
Highly Voted 5 years, 4 months agoMarkusofThere
Most Recent 1 year agoProzac400
1 year, 1 month agoJyoti1010
1 year, 2 months agojasM_123
1 year, 2 months agoDilara22
1 year, 4 months agoChavvakula
1 year, 6 months agojulioglez88
1 year, 6 months agoguojun
2 years, 7 months agotpasha99
2 years, 7 months agoEricSon
3 years, 7 months agothree33
3 years, 8 months agodrugones
3 years, 9 months agoDannyDX
3 years, 9 months agoSatyajitg
3 years, 11 months agomangelesn
3 years, 11 months ago