At the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the definition of `Done`. What two things should happen with the undone Product Backlog item? (Choose two.)
A.
If the stakeholders agree, the Product Owner can accept it and release it to the users.
B.
Put it on the Product Backlog for the Product Owner to decide what to do with it.
C.
Review the item, add the ג€Doneג€ part of the estimate to the velocity and create a Story for the remaining work.
D.
Do not include the item in the Increment this Sprint.
Currently there are no comments in this discussion, be the first to comment!
This section is not available anymore. Please use the main Exam Page.PSM I Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.