Teams can have different start and end date for their respective sprint.Sprint are desired to be aligned.for example one team can have a sprint that is 2 week long and another team working on same project can have a sprint that is 4 week long.
In the book "Scrum and Xp from the trenches" henrik kniberg on the page 103 it is mentioned that " it would be much better to synchronize the sprints "
http://wwwis.win.tue.nl/2R690/2019-2020_Q1/doc/ScrumAndXpFromTheTrenchesonline07-31.pdf
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CopyKing
2 months, 1 week agoJyoti1010
4 months, 1 week agoMi_Windsor
5 months, 4 weeks agoaam1972
1 year, 10 months agoDannyDX
2 years, 11 months agoAnjani2020
2 years, 12 months agoRz_rahgozar
3 years, 3 months agoHershey999
3 years, 1 month agoainaoshokoya
3 years, 9 months agoPebo
3 years, 1 month agounkn0wn4
3 years, 9 months ago