Teams can have different start and end date for their respective sprint.Sprint are desired to be aligned.for example one team can have a sprint that is 2 week long and another team working on same project can have a sprint that is 4 week long.
In the book "Scrum and Xp from the trenches" henrik kniberg on the page 103 it is mentioned that " it would be much better to synchronize the sprints "
http://wwwis.win.tue.nl/2R690/2019-2020_Q1/doc/ScrumAndXpFromTheTrenchesonline07-31.pdf
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CopyKing
1 year agoJyoti1010
1 year, 2 months agoMi_Windsor
1 year, 3 months agoaam1972
2 years, 7 months agoDannyDX
3 years, 9 months agoAnjani2020
3 years, 9 months agoRz_rahgozar
4 years agoHershey999
3 years, 11 months agoainaoshokoya
4 years, 6 months agounkn0wn4
4 years, 6 months agoPebo
3 years, 10 months ago