Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 31 discussion

Actual exam question from Scrum's PSM I
Question #: 31
Topic #: 1
[All PSM I Questions]

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

  • A. When the Product Owner identifies new work.
  • B. As soon as possible after they are identified.
  • C. When the Scrum Master has time to enter them.
  • D. During the Daily Scrum after the Development Team approves them.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
dipsMumbai
Highly Voted 4 years, 6 months ago
Correct answer is B . Explanation is below . https://www.scrum.org/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint
upvoted 11 times
...
EmaEye
Highly Voted 4 years, 6 months ago
I think that D is correct answer
upvoted 7 times
...
okayhey
Most Recent 8 months ago
Selected Answer: D
Gonna go against the grain and say D, since only the developers can change the sprint backlog. Any impediments are also raised during dailies and discussed with the team. No one person can make changes without discussing it as a team.
upvoted 1 times
okayhey
8 months ago
Also since new work needs to be estimated first.
upvoted 1 times
...
...
hiepnb97
8 months, 3 weeks ago
B Sprint Backlog It is a highly visible, real-time picture of the work that the Developers plan to ...
upvoted 1 times
...
Djedjig
9 months, 1 week ago
B is correct
upvoted 1 times
...
Jyoti1010
1 year, 2 months ago
Selected Answer: B
As soon as they are identified.
upvoted 1 times
...
Jyoti1010
1 year, 2 months ago
Option B .As soon as possible after they are identified.
upvoted 1 times
...
Godfall
1 year, 2 months ago
Selected Answer: B
B. As soon as possible after they are identified. The Scrum Guide encourages that new work or further decomposition of work should be added to the Sprint Backlog as soon as it is identified to ensure transparency and flexibility during the Sprint.
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
B is the correct answer
upvoted 1 times
...
aam1972
2 years, 7 months ago
Selected Answer: B
First of all the responsible to make change on the sprint Backlog is the develop team. Second , develop team make a changes to the Backlog during the sprint "Work planned for the first days of the Sprint by the Development Team is decomposed by the end of this meeting, often to units of one day or less. The Development Team self-organizes to undertake the work in the Sprint Backlog, both during Sprint Planning and as needed throughout the Sprint." Conclusion : B: As soon as possible after they are identified.
upvoted 2 times
...
Arend78
3 years, 10 months ago
The question is about "work", not new backlog items/stories. As soon as there is a better understanding of what *work* actually needs to be done, this can/should be added to the Sprint backlog (transparency): https://scrumguides.org/scrum-guide.html#artifacts-sprintbacklog
upvoted 3 times
...
Rz_rahgozar
4 years ago
How the correct answer can B as it is mentioned in Scrum Glossary " the Sprint Backlog is frozen " means that items (stories) in the Sprint Backlog cannot be added or removed during the Sprint. However it might be necessary to get more information, justify or clear some of the items during the Sprint, which should be done in he presence of the Product Owner.
upvoted 2 times
...
Anosa
4 years, 6 months ago
The Answer is B .. https://www.scrum.org/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...