Correct answer is B . Explanation is below .
https://www.scrum.org/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint
Gonna go against the grain and say D, since only the developers can change the sprint backlog. Any impediments are also raised during dailies and discussed with the team. No one person can make changes without discussing it as a team.
B. As soon as possible after they are identified.
The Scrum Guide encourages that new work or further decomposition of work should be added to the Sprint Backlog as soon as it is identified to ensure transparency and flexibility during the Sprint.
First of all the responsible to make change on the sprint Backlog is the develop team.
Second , develop team make a changes to the Backlog during the sprint "Work planned for the first days of the Sprint by the Development Team is decomposed by the end of this meeting, often to units of one day or less. The Development Team self-organizes to undertake the work in the Sprint Backlog, both during Sprint Planning and as needed throughout the Sprint."
Conclusion : B: As soon as possible after they are identified.
The question is about "work", not new backlog items/stories.
As soon as there is a better understanding of what *work* actually needs to be done, this can/should be added to the Sprint backlog (transparency):
https://scrumguides.org/scrum-guide.html#artifacts-sprintbacklog
How the correct answer can B as it is mentioned in Scrum Glossary " the Sprint Backlog is frozen " means that items (stories) in the Sprint Backlog cannot be added or removed during the Sprint. However it might be necessary to get more information, justify or clear some of the items during the Sprint, which should be done in he presence of the Product Owner.
The Answer is B ..
https://www.scrum.org/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
dipsMumbai
Highly Voted 4 years, 6 months agoEmaEye
Highly Voted 4 years, 6 months agookayhey
Most Recent 8 months agookayhey
8 months agohiepnb97
8 months, 3 weeks agoDjedjig
9 months, 1 week agoJyoti1010
1 year, 2 months agoJyoti1010
1 year, 2 months agoGodfall
1 year, 2 months agoMi_Windsor
1 year, 3 months agoaam1972
2 years, 7 months agoArend78
3 years, 10 months agoRz_rahgozar
4 years agoAnosa
4 years, 6 months ago