exam questions

Exam PSPO I All Questions

View all questions & answers for the PSPO I exam

Exam PSPO I topic 1 question 10 discussion

Actual exam question from Scrum's PSPO I
Question #: 10
Topic #: 1
[All PSPO I Questions]

When the Developers determine that they will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

  • A. The Product Owner and all stakeholders.
  • B. The Scrum Master and the Developers.
  • C. The Scrum Master, project manager and the Developers.
  • D. The Product Owner and the Developers.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DUSHIWORLD
1 week ago
Selected Answer: D
The Product Owner plays a key role in adjusting the scope of the Sprint. They work with the Developers to decide which Product Backlog items should be adjusted or removed based on the remaining capacity and priority. The Scrum Master may also facilitate this discussion, ensuring that the team stays aligned with Scrum principles and helps remove any obstacles, but the Product Owner is the person responsible for prioritizing the work. The goal is to ensure that the remaining work in the Sprint is aligned with the highest value and that the Sprint Goal can still be met, even if the full forecast cannot be completed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago