Question #: 29
Topic #: 1
[All PSM I Questions]

As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)

  • A. Recruit additional Development Team members before the work can begin.
  • B. The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress.
  • C. Cancel the Sprint.
  • D. Remove or change selected Product Backlog items.
  • E. The Development Team works overtime during this Sprint.
Show Suggested Answer Hide Answer
Suggested Answer: BD 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
DinithiB
Highly Voted 4 years, 9 months ago
"Scope may be clarified and re-negotiated between the Product Owner and Development Team as more is learned." - Scrum Guide
upvoted 11 times
...
Djedjig
Most Recent 9 months, 1 week ago
B,D are correct
upvoted 1 times
...
Issam_KHELIL
1 year, 1 month ago
Selected Answer: BD
answers : B & D
upvoted 1 times
...
Jyoti1010
1 year, 2 months ago
Selected Answer: BD
Scope of the sprint can be re-negotiated.
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
B and D are correct
upvoted 1 times
...
Atanu_M
3 years, 7 months ago
B & D are correct
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...