exam questions

Exam PSM II All Questions

View all questions & answers for the PSM II exam

Exam PSM II topic 1 question 216 discussion

Actual exam question from Scrum's PSM II
Question #: 216
Topic #: 1
[All PSM II Questions]

Self-management is more effective when it happens within boundaries.

Select two relevant boundaries for self-management provided by the Scrum framework. (Choose two.)

  • A. Timeboxing work to allow for frequent inspection.
  • B. Creating a valuable and useful Increment by the end of each Sprint.
  • C. Having an even number of members in a Scrum Team to be able to do pair programming and be more productive.
  • D. Clearly defining sub-responsibilities and handovers within the Scrum Team.
Show Suggested Answer Hide Answer
Suggested Answer: AD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
wyobrazsobie
1 month, 3 weeks ago
Selected Answer: AB
A and B Scrum emphasizes self-management and shared responsibility. Sub-responsibilities and handovers contradict this by creating unnecessary silos and dependencies.
upvoted 1 times
...
vl88
5 months, 2 weeks ago
Selected Answer: AB
Question is about boundaries. D has nothing to do with it
upvoted 1 times
...
Walencule
5 months, 3 weeks ago
Answer = A&B
upvoted 1 times
...
OMG4567
6 months, 2 weeks ago
Selected Answer: AB
Clearly A&B
upvoted 1 times
...
Timmbuktu
7 months ago
Clearly, it is A & B
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago