The best answer is: C. Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.
Explanation: In Scrum, when multiple Scrum Teams work on the same product, their Increments must be integrated every Sprint to ensure that stakeholders and the Product Owner can inspect a usable and potentially releasable product. This supports empiricism, transparency, and continuous feedback.
This section is not available anymore. Please use the main Exam Page.PSPO I Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
nervesjangles4
1 month agoBo8
10 months, 1 week agoHaraTadahisa
10 months, 1 week ago