The best answer is: C. Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.
Explanation: In Scrum, when multiple Scrum Teams work on the same product, their Increments must be integrated every Sprint to ensure that stakeholders and the Product Owner can inspect a usable and potentially releasable product. This supports empiricism, transparency, and continuous feedback.