You are the Scrum Master for a Scrum Team whose Daily Scrum is scheduled to start at 10:00 each day. Developers routinely turn up late, and once everyone has assembled, the Daily Scrum starts. By then it is typically 4 to 5 minutes later than scheduled. Other meetings in the organization typically allow 4 to 5 minutes for people to transport within the building.
Some Developers complain that it is now hard to achieve the purpose of the Daily Scrum within the timebox, since there is only 10 or 11 minutes left after waiting for people to show up. The Developers ask for your advice.
vl88
2 months, 4 weeks agoWalencule
3 months, 1 week agoOMG4567
4 months agoAmeet9
7 months, 1 week agoWalencule
3 months, 1 week agoOMG4567
4 months ago