When can a Development Team cancel a Sprint?

  • A. When a technical dependency cannot be resolved.
  • B. When the selected Product Backlog items for the Sprint become unachievable.
  • C. When the Product Owner is absent too often.
  • D. It cannot. Only Product Owners can cancel Sprints.
  • E. When functional expectations are not well understood.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Yassine_PO
7 months, 3 weeks ago
Selected Answer: D
A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...