The Development Team should have all the skills needed to:

  • A. Turn Product Backlog items into a valuable, useful Increment.
  • B. Do all of the development work, except for specialized testing that requires additional tools and environments.
  • C. Complete the project within the date and cost as calculated by the Product Owner.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
hiepnb97
8 months, 3 weeks ago
Selected Answer: A
"Scrum Teams are cross-functional, meaning the members have all the skills necessary to create value each Sprint."
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...