Actual exam question from Scrum's PSPO I
Question #: 17
Topic #: 1
[All PSPO I Questions]

A Product Owner is accountable for maximizing the value of the product that is the result of the Work of the Scrum Team. Which of the following can be delegated to others, while the Product Owner remains accountable for the work? (Choose two.)

  • A. Attending the Sprint Retrospective.
  • B. Attending the Sprint Review.
  • C. Ordering Product Backlog items.
  • D. Developing and communicating the Product Goal.
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Virgo1990
1 month ago
C and D is Correct
upvoted 1 times
...
Jimmystuff
4 months, 1 week ago
Selected Answer: CD
C & D because the guide says: 'The Product Owner is also accountable for effective Product Backlog management, which includes: ● --->Developing and explicitly communicating the Product Goal; ● Creating and clearly communicating Product Backlog items; ● --->Ordering Product Backlog items; and, ● Ensuring that the Product Backlog is transparent, visible and understood. The Product Owner may do --->the above work or may delegate the responsibility to others. Regardless, the Product Owner remains accountable."
upvoted 2 times
...
horton
7 months, 1 week ago
Selected Answer: AD
According to the Scrum Guide, PO is not required for the Sprint Retrospective, but Sprint Review. So, the only answers left for this questions are A and D.
upvoted 1 times
...
Pattabiraman
8 months, 3 weeks ago
Sprint retro is mandatory for the PO to attend. Not sure of the right answers.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...