Exam PSM II topic 1 question 46 discussion

Actual exam question from Scrum's PSM II
Question #: 46
Topic #: 1
[All PSM II Questions]

During the Sprint Review, the Product Owner decides to release the current Increment to production. The stakeholders suggest temporarily delaying the next
Sprint in order to respond more quickly to user feedback after the release. The Product Owner prefers to continue to the next Sprint and make progress towards the next release. Steven, the Scrum Master, begins facilitating the discussion.
What would be two acceptable outcomes of the discussion? (Choose two.)

  • A. Continue with the Sprints and include the customer feedback in the Product Backlog.
  • B. Delay the next Sprint to allow the Development Team to work on new customer feedback.
  • C. Continue with the Sprints but shorten the Sprint time-boxes to allow for shorter feedback loops.
  • D. Continue with the Sprints but allow the Sprint Goal within the Sprint to change according to the customer feedback.
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️
A new Sprint starts immediately after the conclusion of the previous Sprint. Delaying the start of the next Sprint interrupts progress and can reduce the Time-to-
Market. Shortening the Sprint length allows the team to respond quicker to changes outside of the Sprint plan and while still allowing delivery of business value.
Adding user feedback to the Product Backlog helps the Product Owner with ordering the backlog to maximize the flow of value.
During the Sprint no changes are made that would endanger the Sprint Goal.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mbouzidi
4 months ago
Selected Answer: AC
A C are the best options
upvoted 1 times
...
OMG4567
4 months ago
Selected Answer: AC
In my opinion the sprint goal must not be changed during sprint. (Quote from Scrum Guide: "If the work turns out to be different than they expected, they collaborate with the Product Owner to negotiate the scope of the Sprint Backlog within the Sprint without affecting the Sprint Goal." Page 11)
upvoted 1 times
...
LuckyAro
10 months ago
Selected Answer: AD
A & D Makes more sense to me.
upvoted 1 times
Mbouzidi
4 months ago
D is not possible, the sprint goal don't change on scrum
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.