Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 214 discussion

Actual exam question from Scrum's PSM I
Question #: 214
Topic #: 1
[All PSM I Questions]

Who does the work to make sure Product Backlog items conform to the Definition of Done? (Choose the best answer.)

  • A. The Quality Assurance Team.
  • B. The Scrum Master.
  • C. The Developers
  • D. The Product Owner.
  • E. The Scrum Team.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jyoti1010
1 year, 1 month ago
Selected Answer: C
C is correct.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...