When does a Sprint conclude? (Choose the best answer.)

  • A. When all Product Backlog items meet their Definition of Done.
  • B. When the Sprint Retrospective is complete.
  • C. When the Product Owner decides enough has been delivered to meet the Sprint Goal.
  • D. When all the tasks are completed by the Developers.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
emelba
10 months, 3 weeks ago
When the timebox expires = When the Sprint Retrospective is complete.
upvoted 1 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: B
When sprint retrospective is completed.
upvoted 2 times
...
UppersquareCapital
1 year, 2 months ago
Correct Answer is B - When the Sprint Retrospective is complete. According to the Scrum Guide, A Sprint is timeboxed and is over whenever its timebox expires. The Sprint Retrospective is the final event of the Sprint, hence it concludes the Sprint.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...