Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 5 discussion

Actual exam question from Scrum's PSM I
Question #: 5
Topic #: 1
[All PSM I Questions]

When is a Sprint over?

  • A. When the Product Owner says it is done.
  • B. When all Product Backlog items meet their definition of ג€Doneג€.
  • C. When all the tasks are completed.
  • D. When the time-box expires.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://www.extremeuncertainty.com/in-scrum-when-is-a-sprint-over/#:~:text=The%20short%20and%20simple%20answer,%2C%20one%20week%2C
%20etc

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
maverick_walker
7 months ago
D is correct
upvoted 1 times
...
Djedjig
9 months, 1 week ago
D is correct
upvoted 1 times
...
Jyoti1010
1 year, 2 months ago
Option D is correct.Each scrum event is time boxed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...