After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance and complains to the Product Owner. The
Product Owner comes to the Scrum Master asking for advice.
What is the best action for a Scrum Master to take?

  • A. Wait until the next Sprint Retrospective as it is the most opportune time to modify the Definition of Done.
  • B. Bring the concern to the testers in the Development Team and ask them to include performance testing.
  • C. Explain to the Product Owner that it's up to the Development Team to. decide on acceptable performance standards as they own the Definition of Done.
  • D. Encourage the Product Owner to bring the performance concerns to the Development Team and work with them on how to improve performance, and ultimately have stronger Definition of Done.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
The highest priority of agility is to satisfy the customer through early and continuous delivery of valuable software. Because the Development Team is the one doing the work and increments must meet performance standards, they can expand their Definition of Done to include more stringent criteria for higher quality.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mbouzidi
2 months, 3 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
Coco001
1 year, 1 month ago
For answer D when is this done, when is the DOD reviewed, isn’t not during retrospective?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...