Exam PSM I topic 1 question 23 discussion

Actual exam question from Scrum's PSM I
Question #: 23
Topic #: 1
[All PSM I Questions]

Which outcome is expected as Scrum Teams mature?

  • A. They will improve their definition of ג€Doneג€ to include more stringent criteria.
  • B. The Sprint Retrospectives will grow to be longer than 4 hours.
  • C. There is no need for a time-boxed Sprint.
  • D. Sprint Reviews will no longer be needed.
  • E. A Scrum Master is no longer needed since they are a mature team now.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Djedjig
9 months, 1 week ago
A is correct
upvoted 1 times
...
Issam_KHELIL
1 year, 1 month ago
Selected Answer: A
The correct answer is A
upvoted 2 times
...
Jyoti1010
1 year, 2 months ago
Selected Answer: A
With more functional requirements comes the non functional requirements.These non functional requirements are added to Definition of Done and it become more stringent.
upvoted 2 times
...
Mi_Windsor
1 year, 3 months ago
A is the correct answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...