Exam PSM I topic 1 question 104 discussion

Actual exam question from Scrum's PSM I
Question #: 104
Topic #: 1
[All PSM I Questions]

As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

  • A. Inform the Product Owner at the Sprint Review, but prior to the demonstration.
  • B. Find another Scrum Team to give the excess work to.
  • C. As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.
  • D. Reduce the definition of ג€Doneג€ and get all of the Product Backlog items ג€Doneג€ by the new definition.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jyoti1010
1 year, 2 months ago
Selected Answer: C
Sprint goal is fixed but scope can be renegotiated and updated.
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
C is the correct answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...