why the other options are incorrect:
The Development Team is responsible for conducting the Daily Scrum.
A. Lead the discussions of the Development Team: The Scrum Master does not lead the discussions of the Development Team. The Daily Scrum is a self-organizing meeting.
I am confident that both options B and D are correct. While we are required to choose only one option, it's worth noting that option E, 'All of the above,' encompasses both correct choices. Therefore, selecting option E ensures that we acknowledge the correctness of both B and D.
All of the above.
Scrum Master's involvement in leading discussions, ensuring all questions are answered, monitoring team members' participation, and teaching time-boxing aligns with their roles.
This section is not available anymore. Please use the main Exam Page.PSM I Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
e6b0f54
5 months, 2 weeks agoQuinns_
1 year agohiepnb97
1 year, 1 month agoDela803
1 year, 2 months agoLuckyAro
1 year, 2 months agosdecoster
1 year, 2 months agoJyoti1010
1 year, 6 months agoMi_Windsor
1 year, 8 months ago