The Sprint Review is mainly an inspect and adapt opportunity for which group?

  • A. The Development Team and stakeholders.
  • B. The Product Owner and Development Team.
  • C. The Scrum Team and stakeholders.
  • D. The Product Owner and management.
  • E. The Development Team and management.
  • F. The Product Owner and stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://www.scrum.org/forum/scrum-forum/15111/po-optimizing-value-work-development-team-performs#:~:text=Optimizing%20the%20value%20of%20the%
20work%20the%20Development%20Team%20performs%3B,-%E2%80%A2&text=Ensuring%20that%20the%20Product%20Backlog,will%20work%20on%20next
%3B%20and%2C&text=Ensuring%20the%20Development%20Team%20understands,Backlog%20to%20the%20level%20needed

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jyoti1010
1 year, 2 months ago
Selected Answer: C
C is correct
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
C is the correct answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.