Question #: 74
Topic #: 1
[All PSM I Questions]

How is management external to the Scrum Team involved in the Daily Scrum?

  • A. The Scrum Master speaks on their behalf.
  • B. Managers are not required at the Daily Scrum.
  • C. Management gives an update at the start of each Daily Scrum.
  • D. The Product Owner represents their opinions.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://chercher.tech/agile-certification/scrum-master-certification-prep-questions-set-7

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ceausorin
2 months, 2 weeks ago
Why not D?
upvoted 1 times
ficklesena
2 months, 1 week ago
Product Owner is not attending Daily Scrum, only developers
upvoted 2 times
...
...
Jyoti1010
3 months ago
Daily scrum is attended by the developers only.
upvoted 2 times
...
Mi_Windsor
4 months, 3 weeks ago
Why not D? Please explain
upvoted 2 times
yasir_34z
1 month, 3 weeks ago
The question focuses on Daily Scrum, and Product Owner is a representative of the management but he is not required to attend Daily Scrum.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago