Exam PSM I topic 1 question 73 discussion

Actual exam question from Scrum's PSM I
Question #: 73
Topic #: 1
[All PSM I Questions]

If burndown charts are used to visualize progress, what do they track?

  • A. Accumulated cost.
  • B. Individual worker productivity.
  • C. Work remaining across time.
  • D. Accumulated business value delivered to the customer.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://zepel.io/agile/reports/burndown/#:~:text=Essentially%2C%20a%20burndown%20chart%20is,through%E2%80%9D%20tasks%20in%20a%
20sprint

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jyoti1010
1 year, 2 months ago
Selected Answer: C
C.Burn-down chart shows the work remaining.
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
C is the correct answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...