Actual exam question from Scrum's PSM I
Question #: 48
Topic #: 1
[All PSM I Questions]

Who is responsible for managing the progress of work during a Sprint?

  • A. The Scrum Master.
  • B. The Development Team.
  • C. The Product Owner.
  • D. The most junior member of the Team.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.aha.io/roadmapping/guide/release-management/what-is-a-sprint#:~:text=Who%20manages%20a%20sprint%3F,in%20sprint%20planning
%20and%20implementation.&text=Responsible%20for%20maximizing%20the%20value,to%20accept%20stories%20as%20done

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
maverick_walker
7 months ago
B is correct
upvoted 1 times
...
okayhey
8 months ago
Selected Answer: B
B, dev team is self-managing, Scrum master only ensures Scrum is correctly applied
upvoted 1 times
...
Quinns_
8 months, 1 week ago
A is the correct answer The Scrum Master is responsible for managing the progress of work during a Sprint. They guide and support the team to achieve their sprint goals and follow the Scrum framework.
upvoted 2 times
...
Mi_Windsor
1 year, 3 months ago
B is the correct answer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...