Who starts the Daily Scrum?

  • A. The person coming in last. This encourages people to be on time and helps to stay within the time-box.
  • B. Whoever the Development Team decides should start.
  • C. The person who has the token.
  • D. The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.
  • E. The person who last broke the build.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://effectussoftware.com/blog/how-to-create-value-daily-scrum-meeting/#:~:text=Who%20starts%20the%20Daily%20Scrum,discussed%20during%
20the%2015%20minutes

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
maverick_walker
7 months ago
B is correct
upvoted 1 times
...
Jyoti1010
1 year, 2 months ago
Selected Answer: B
B is correct.
upvoted 1 times
...
Mi_Windsor
1 year, 3 months ago
B is the correct answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...