Question #: 32
Topic #: 1
[All PSM I Questions]

What is the main reason for the Scrum Master to be at the Daily Scrum?

  • A. To gather status and progress information to report to management.
  • B. To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.
  • C. They do not have to be there; they only need to ensure the Development Team has a Daily Scrum.
  • D. To make sure every team member answers the three questions.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
maris478
1 month, 4 weeks ago
This is one annoying question. The question isn't about whether Scrum master have to or does not have to be present at the Daily scrum. To which C would sound like a great answer. The question though implies that Scrum master is attending Daily scrum (or at least is planning to attend) and asks for a reason why would he do so. To which D (kind of) seems like a decent choice. Yet everywhere I see this question it's always C.
upvoted 1 times
...
maverick_walker
6 months, 3 weeks ago
D is correct
upvoted 1 times
...
Djedjig
9 months ago
C is correct
upvoted 1 times
...
k17sun3
1 year, 1 month ago
Selected Answer: C
Option C is correct. The open assessment exam has the same question and the answer is C.
upvoted 3 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: C
Option C is correct.Only developers are present.
upvoted 3 times
...
Godfall
1 year, 2 months ago
Selected Answer: D
D. To make sure every team member answers the three questions. The Daily Scrum is a time for the Development Team to inspect progress and adapt their plan for the next 24 hours. The Scrum Master's role in the Daily Scrum is to ensure that it is conducted effectively and to facilitate the meeting. They do not attend to gather status information for reporting to management (option A), write down changes to the Sprint Backlog (option B), or simply ensure that the meeting happens (option C). Instead, their primary focus is on helping the team with their interactions and by removing any impediments that may be blocking progress.
upvoted 2 times
...
Mi_Windsor
1 year, 2 months ago
Should the answer not be C? SM don’t have to be present
upvoted 2 times
...
Albinopreto
1 year, 4 months ago
La réponse correcte est : D. S'assurer que chaque membre de l'équipe répond aux trois questions. Le rôle principal du Scrum Master lors du Daily Scrum est de faciliter la réunion et de s'assurer que l'équipe suit le format et répond aux trois questions clés du Daily Scrum : Qu'est-ce que j'ai accompli depuis la dernière Daily Scrum ? Qu'est-ce que j'ai l'intention d'accomplir d'ici la prochaine Daily Scrum ? Quels obstacles m'empêchent d'atteindre mes objectifs ?
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...