What is the timebox for the Sprint Review?

  • A. As long as needed.
  • B. 2 hours for a one-month Sprint.
  • C. 4 hours for a one-month Sprint.
  • D. 1 day
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://www.visual-paradigm.com/scrum/what-are-scrum-time-boxed-events/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jyoti1010
1 year, 2 months ago
Selected Answer: C
A time box event of 4 hours for a month long sprint.
upvoted 1 times
...
JoshyKawasaki
1 year, 5 months ago
Correct Answer is C. Should cite Scrum Guide instead. "The Sprint Review is the second to last event of the Sprint and is timeboxed to a maximum of four hours for a one-month Sprint. For shorter Sprints, the event is usually shorter." https://scrumguides.org/scrum-guide.html
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...