Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 24 discussion

Actual exam question from Scrum's PSM I
Question #: 24
Topic #: 1
[All PSM I Questions]

When must a Scrum Team release each Increment?

  • A. When it makes sense to release it.
  • B. When the Scrum Team finishes their work.
  • C. Whenever the product is free of defects.
  • D. After every Sprint, without exception.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
maverick_walker
6 months, 3 weeks ago
A is correct
upvoted 1 times
...
okayhey
7 months, 3 weeks ago
Selected Answer: A
A is without a doubt correct
upvoted 1 times
...
MarcoScaramelli
9 months ago
Answer is D, an increment must be released at the end of each sprint. Then it can be delivered to users/market when the prod owner decides that it makes sense.
upvoted 1 times
e6b0f54
1 month, 1 week ago
If you support D, you better look into the scrum guide again.
upvoted 1 times
...
okayhey
7 months, 4 weeks ago
No it doesn't, it just needs to meet the definition of done. It's up to the PO to release it or not. An increment is a POTENTIALLY releasable piece of software.
upvoted 1 times
...
...
Djedjig
9 months ago
A is correct
upvoted 1 times
...
Issam_KHELIL
1 year, 1 month ago
Selected Answer: A
Answer A is correct
upvoted 1 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: A
Scrum team can decide when to release an increment.They not necessarily need to wait for review.The moment any sprint backlog item conform the Definition of Done , a new increment is born.
upvoted 3 times
...
Cliu
1 year, 2 months ago
Selected Answer: A
Increment should be releasable, but not necessarily to be released
upvoted 4 times
...
Godfall
1 year, 2 months ago
Selected Answer: A
Based on the Scrum Guide, the answer to the question "When must a Scrum Team release each Increment?" is: A. When it makes sense to release it. Scrum Teams are encouraged to release increments of the product as soon as it makes sense to do so, based on their product's goals and customer needs. There is no strict requirement to release after every Sprint, and it should be driven by the business value and timing considerations rather than being tied to a fixed schedule.
upvoted 2 times
...
293ebce
1 year, 3 months ago
Correct Answer is A. During the Sprint Product Backlog Item(s) turn into Increment(s). They meet the definition of "Done". An Increment can be released now, or later - at any given time. Releasing means putting value in the hands of customers.
upvoted 2 times
...
Luchito
1 year, 4 months ago
Selected Answer: D
According to the Scrum Guide, each increment must be released at the end of each Sprint, regardless of whether or not it is shipped to customers.
upvoted 2 times
amit_swolf
1 year, 2 months ago
this is google's top result but its incorrect. when product backlog item reaches DoD, it can be released at any point. A is correct
upvoted 1 times
...
Marty10
1 year, 3 months ago
So then it can't be released AFTER the sprint I think?!
upvoted 1 times
...
...
RamanAgarwal
1 year, 5 months ago
Correct Answer is Option D. We should release the increment at the end of every sprint. Doesnt need to go to production
upvoted 1 times
JoshyKawasaki
1 year, 4 months ago
Answer is A. Ultimate goal of each sprint is to produce an increment of value. PO makes the decision as to if/when it is released. It is not a mandatory requirement at the end of each sprint.
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...