It's C. - ownership of Sprint Backlog items is shared by the entire Development Team. The team works collaboratively and collectively takes responsibility for delivering the Sprint Goal.
According to the Scrum Guide,
"Sprint Planning addresses the following topic: What can be Done this Sprint?
...Through discussion with the Product Owner, the Developers select items from the Product Backlog to include in the current Sprint."
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Chavvakula
Highly Voted 1 year, 8 months agookayhey
10 months, 2 weeks agoBJD1199
Most Recent 1 week, 3 days agoe6b0f54
3 months, 4 weeks agomaverick_walker
9 months, 1 week agookayhey
10 months, 1 week agoDjedjig
11 months, 3 weeks agoMARWA_
1 year agoThedragon123
1 year, 1 month agoWeazzlyy
1 year, 3 months agoPRINZVONBRAZILIEN
1 year, 3 months agoJyoti1010
1 year, 4 months agoalsheydane13
1 year, 6 months agookayhey
10 months, 1 week agoMi_Windsor
1 year, 6 months ago