exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 15 discussion

Actual exam question from Scrum's PSM I
Question #: 15
Topic #: 1
[All PSM I Questions]

When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)

  • A. At the Sprint planning meeting.
  • B. During the Daily Scrum.
  • C. Never. All Sprint Backlog Items are ג€ownedג€ by the entire Scrum Team.
  • D. Whenever a team member can accommodate more work.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Chavvakula
Highly Voted 1 year, 8 months ago
As "The Sprint Backlog is a plan by and for the Developers." i think the answer is Option A.
upvoted 6 times
okayhey
10 months, 2 weeks ago
The answer is literally in your comment and you still choose A....
upvoted 1 times
...
...
BJD1199
Most Recent 1 week, 3 days ago
Selected Answer: C
It's C. - ownership of Sprint Backlog items is shared by the entire Development Team. The team works collaboratively and collectively takes responsibility for delivering the Sprint Goal.
upvoted 1 times
...
e6b0f54
3 months, 4 weeks ago
Selected Answer: C
The whole team owns.
upvoted 1 times
...
maverick_walker
9 months, 1 week ago
C is correct
upvoted 1 times
...
okayhey
10 months, 1 week ago
Selected Answer: C
C, sprint Backlog is never owned by an individual but by all developers
upvoted 1 times
...
Djedjig
11 months, 3 weeks ago
C is correct
upvoted 2 times
...
MARWA_
1 year ago
It's C
upvoted 1 times
...
Thedragon123
1 year, 1 month ago
Selected Answer: C
its C! i'm 100% sure
upvoted 1 times
...
Weazzlyy
1 year, 3 months ago
Selected Answer: C
It's C. This is a question in the practice exam on scrum.org.
upvoted 1 times
...
PRINZVONBRAZILIEN
1 year, 3 months ago
It caused me doubts, beetwen A and C.
upvoted 1 times
...
Jyoti1010
1 year, 4 months ago
Option C
upvoted 3 times
...
alsheydane13
1 year, 6 months ago
Selected Answer: A
According to the Scrum Guide, "Sprint Planning addresses the following topic: What can be Done this Sprint? ...Through discussion with the Product Owner, the Developers select items from the Product Backlog to include in the current Sprint."
upvoted 2 times
okayhey
10 months, 1 week ago
That's talking about selecting items to include in the sprint, but the question is who owns the sprint backlog and that's the developers as a whole.
upvoted 1 times
...
...
Mi_Windsor
1 year, 6 months ago
C is the correct answer
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago