Exam PSM I topic 1 question 83 discussion

Actual exam question from Scrum's PSM I
Question #: 83
Topic #: 1
[All PSM I Questions]

The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.

  • A. False.
  • B. True, accordingly to what was committed to the stakeholders.
  • C. True, but only after confirmation by the resource manager that the Team has enough capacity.
  • D. True.
  • E. False, the Scrum Master does that.
  • F. False, capacity and commitment are the Project manager's responsibility.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://medium.com/serious-scrum/who-decides-what-goes-in-the-sprint-backlog-4573ad9e1d57

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
CopyKing
1 year ago
Selected Answer: A
The Dev team decided what they will work on during the sprint. But the PO will manage the product backlog.
upvoted 1 times
...
Jyoti1010
1 year, 2 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
Albinopreto
1 year, 4 months ago
Non, en général, ce n'est pas le rôle du Product Owner de déterminer le nombre d'éléments du Product Backlog que l'équipe de développement sélectionne pour un Sprint. Le Product Owner est responsable de la gestion du Product Backlog, qui est une liste ordonnée des fonctionnalités, des améliorations, des corrections de bugs et d'autres éléments qui représentent la vision du produit.
upvoted 2 times
...
Chavvakula
1 year, 6 months ago
As per me the answer is C : True as PO is responsible for managing Product backlog and he is not outside of scrum team.
upvoted 1 times
JoshyKawasaki
1 year, 5 months ago
Answer is A, False. Cannot be E - Developers select product backlog items for Sprint backlog, not PO Cannot be F - There is no PM in Scrum "For each selected Product Backlog item, the Developers plan the work necessary to create an Increment that meets the Definition of Done. This is often done by decomposing Product Backlog items into smaller work items of one day or less. How this is done is at the sole discretion of the Developers. No one else tells them how to turn Product Backlog items into Increments of value." (Section under Sprint Planning) https://scrumguides.org/scrum-guide.html
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.