When must the Product Owner participate in the Daily Scrum?

  • A. When the Product Owner needs to represent the stakeholders' point of view to the Developers.
  • B. When there are impediments to discuss.
  • C. When the Scrum Master asks the Product Owner to attend.
  • D. When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Amrx
4 months, 4 weeks ago
Selected Answer: D
Scrum Guide says If the Product Owner or Scrum Master are actively working on items in the Sprint Backlog, they participate as Developers.
upvoted 1 times
...
Hilary95
1 year ago
Selected Answer: D
Answer D, according to scrum guide .
upvoted 2 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: D
Daily scrum is for developers.D is the right answer.Scrum master and Product owner attend daily scrum only If they are working on sprint backlog item.They participate as developer.
upvoted 3 times
...
plamfor
1 year, 2 months ago
If the Product Owner or Scrum Master are actively working on items in the Sprint Backlog, they participate as Developers. If the Scrum master or product owner is actively working on product backlog items, he or she is expected to both attend and participate in the daily Scrum
upvoted 2 times
...
reika1914
1 year, 3 months ago
Selected Answer: A
The correct answer is A
upvoted 1 times
...
Albinopreto
1 year, 3 months ago
D. Lorsque le Product Owner travaille activement sur des éléments du Sprint Backlog ; cependant, ils participent en tant que développeur. Le Daily Scrum est une réunion quotidienne du Scrum où les membres de l'équipe de développement se réunissent pour synchroniser leur travail et planifier les activités pour la journée. Le Product Owner peut participer au Daily Scrum en tant qu'observateur, mais il ne doit pas être considéré comme une partie prenante régulière de cette réunion car il n'est pas directement impliqué dans la réalisation des tâches quotidiennes.
upvoted 3 times
...
ObeObeObe
1 year, 6 months ago
Selected Answer: A
Agree with A
upvoted 2 times
...
Bhalo
1 year, 6 months ago
This answer is incorrect. it should be A
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...