Question #: 72
Topic #: 1
[All PSM I Questions]

A product Increment must be released to production at the end of each Sprint.

  • A. True
  • B. False
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
CopyKing
12 months ago
B. Its not required at the end of each sprint.
upvoted 1 times
...
SGN63
1 year, 1 month ago
Selected Answer: B
B is the right answer
upvoted 2 times
...
Jyoti1010
1 year, 2 months ago
Selected Answer: B
Option B
upvoted 2 times
...
Albinopreto
1 year, 4 months ago
Un "Incrément" se réfère au cumul de tous les éléments du Backlog Produit terminés au cours d'un Sprint, ainsi que les incréments de tous les Sprints précédents, dans le cadre du développement Agile de logiciels en utilisant Scrum. À la fin de chaque Sprint, un Incrément potentiellement livrable doit être produit. Cependant, il n'est pas nécessaire de mettre l'Incrément en production à la fin de chaque Sprint. La décision de déployer l'Incrément en production est prise par le Product Owner et les parties prenantes en fonction de divers facteurs, notamment la préparation du produit, les priorités commerciales et les risques éventuels associés à la mise en production. Ainsi, la déclaration correcte est : Un Incrément du produit doit être potentiellement livrable, mais pas nécessairement mis en production à la fin de chaque Sprint. donc faux
upvoted 3 times
...
ordealba
1 year, 6 months ago
Selected Answer: A
4.3 Value Driven Delivery. Decrease uncertainty and constantly address risks that can potentially decrease value if they materialize. Also work closely with project stakeholders showing them "product increments" at the end of each Sprint, enabling effective management of changes
upvoted 2 times
JoshyKawasaki
1 year, 5 months ago
Correct answer is B. Watch out for tricky wording... Scrum guide does not explicitly state an increment must be 'released to production', but only useable (meeting the DoD). 'Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism. However, an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value. Work cannot be considered part of an Increment unless it meets the Definition of Done.' - Scrum Guide (under increment section) https://scrumguides.org/scrum-guide.html
upvoted 7 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...