Exam PSM I topic 1 question 216 discussion

Actual exam question from Scrum's PSM I
Question #: 216
Topic #: 1
[All PSM I Questions]

Which two things should the Scrum Team do during the first Sprint? (Choose two.)

  • A. Make up a plan for the rest of the project.
  • B. Define the major product features and a release plan architecture.
  • C. Build at least one piece of valuable functionality.
  • D. Analyze, describe, and document the requirements for the subsequent Sprints.
  • E. Create at least one valuable, useful Increment.
Show Suggested Answer Hide Answer
Suggested Answer: CE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
emelba
6 months, 2 weeks ago
Selected Answer: CE
D is incorrect
upvoted 1 times
...
Gataparda
7 months, 3 weeks ago
Based in Scrum Guide 2020 C & E
upvoted 1 times
...
ceausorin
9 months ago
Selected Answer: CE
Agree with C & E
upvoted 1 times
...
Jyoti1010
9 months, 1 week ago
Selected Answer: CE
C and E
upvoted 1 times
...
Albinopreto
11 months, 2 weeks ago
<B. Définir les principales fonctionnalités du produit et une architecture de plan de version. E. Créez au moins un incrément précieux et utile. Lors du premier Sprint, l'équipe Scrum travaille sur une sélection de fonctionnalités préalablement définies dans le Product Backlog, et elle doit se concentrer sur la création d'un incrément de produit fonctionnel, utile et potentiellement livrable. L'équipe commence également à planifier la manière dont les fonctionnalités seront développées et livrées dans les versions futures (plan de version), ce qui est essentiel pour guider le développement tout au long du projet Scrum. Les autres options ne sont pas des activités typiques du premier Sprint.
upvoted 1 times
...
George103
1 year ago
Selected Answer: CE
C And E!
upvoted 3 times
...
Numba1
1 year, 1 month ago
Selected Answer: CE
that's the answer
upvoted 2 times
...
ObeObeObe
1 year, 1 month ago
Selected Answer: CE
Agree with C & E
upvoted 3 times
...
Bhalo
1 year, 1 month ago
Right answer is C & E
upvoted 3 times
...
imEmi
1 year, 2 months ago
It should be CE
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago