During the Sprint, the Scrum Master’s role is to do which two of the following: (Choose two.)

  • A. Ensure the Product Owner attends all Scrum events.
  • B. Facilitate inspection and adaptation opportunities as requested or needed.
  • C. Assign tasks with the Scrum Team.
  • D. Monitor the progress of the Developers.
  • E. Coaching the team members in self-management.
  • F. Escalate team conflicts to functional line managers.
Show Suggested Answer Hide Answer
Suggested Answer: BE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ObeObeObe
Highly Voted 7 months ago
Selected Answer: BE
Definately BE
upvoted 10 times
...
Manyak2023
Highly Voted 7 months, 3 weeks ago
I think BE
upvoted 8 times
imEmi
7 months, 3 weeks ago
Yes, it's BE!
upvoted 7 times
...
...
Gataparda
Most Recent 1 month, 1 week ago
B & E Developers are Selbst- Organized
upvoted 1 times
...
Jyoti1010
2 months, 3 weeks ago
Selected Answer: BE
B and E
upvoted 2 times
...
Albinopreto
4 months, 4 weeks ago
B. Faciliter les opportunités d'inspection et d'adaptation selon les demandes ou les besoins : Le Scrum Master facilite les réunions et les événements Scrum, tels que les Daily Scrum, la Revue de Sprint et la Rétrospective de Sprint, afin que l'équipe puisse inspecter l'avancement du travail et s'adapter en conséquence. E. Coaching des membres de l'équipe dans l'autogestion : Le Scrum Master guide l'équipe dans l'auto-organisation et l'autogestion. Il les aide à prendre des décisions collectives, à résoudre les problèmes et à devenir de plus en plus autonomes.
upvoted 3 times
...
Safirah
5 months ago
Should be BE
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago