Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PSM I All Questions

View all questions & answers for the PSM I exam

Exam PSM I topic 1 question 49 discussion

Actual exam question from Scrum's PSM I
Question #: 49
Topic #: 1
[All PSM I Questions]

A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what `Done` means. (Choose two.)

  • A. All work the Development Team is willing to do.
  • B. Ready for integration.
  • C. No work left from the definition of ג€Doneג€.
  • D. Whatever the Product Owner defines as quality.
  • E. Ready to be released to end users.
Show Suggested Answer Hide Answer
Suggested Answer: CE 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
okayhey
8 months ago
Selected Answer: CE
CE, an increment is only done when it meets the definition of done, meaning they're is no work left. The definition of done is a shared understanding within the Scrum team and isn't based on what the devs are willing to do. It should be ready to release to users, which does not mean it WILL be released, that's up to the PO. Through CI/CD pipeline, increments are continuously integrated with previous increments.
upvoted 2 times
...
Nolos83
1 year ago
Selected Answer: CE
C and E Not B = The increment must be already integrated
upvoted 2 times
...
Nolos83
1 year ago
C and E Not B = The increment must be already integrated
upvoted 1 times
...
Prozac400
1 year, 1 month ago
B and E Option A is not accurate because "Done" does not mean all work the Development Team is willing to do; it has specific criteria. Option C is redundant, as it essentially restates the concept of "Done." Option D is not entirely accurate, as the Product Owner has input into the Definition of Done, but it is a shared understanding within the Scrum Team and not solely defined by the Product Owner.
upvoted 1 times
...
Jyoti1010
1 year, 1 month ago
Selected Answer: CE
CE are the right options.
upvoted 2 times
...
julioglez88
1 year, 6 months ago
Selected Answer: BC
The correct answers are B and C. Ready for integration: The Increment must be in a state where it can be integrated with other parts of the product. No work left from the definition of "Done": The Increment must meet all of the criteria in the team's definition of "Done". Why is not E: E. Ready to be released to end users: The Increment must be in a state where it can be released to end users, but it does not have to be released at the end of the Sprint.
upvoted 4 times
...
Pinha
1 year, 7 months ago
BC Option B emphasizes that the work completed during the Sprint must be ready for integration with the rest of the product. This means that the work completed by the Development Team should be tested and verified, and any dependencies or conflicts with other parts of the product should be resolved. Option C highlights that there should be no incomplete or unfinished work left from the Definition of Done. The DoD is an agreed-upon set of criteria that the Development Team and the Product Owner define at the beginning of the project. It outlines the quality standards that must be met for the work to be considered "Done." Option E is not entirely correct because being "Ready to be released to end-users" is a subset of the DoD. The work must meet all the criteria outlined in the DoD, including testing, integration, and documentation, to be considered "Done."
upvoted 4 times
xcjxcj
10 months ago
You mean both 'integration' and 'ready to release' are part of dod? Then why not E
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...