Question #: 16
Topic #: 1
[All SAFe Scrum Master Questions]

According to SAFe, which of the following metrics are reported at the Inspect and Adapt event?

  • A. Cumulative value measure
  • B. ART predictability measure
  • C. ART cycle velocity
  • D. Cumulative value rate
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Tygrins
4 days, 20 hours ago
Selected Answer: B
PI Predictability Measure Purpose: Measures how well teams and the ART deliver on their planned objectives. Metric: Calculated as the percentage of business value achieved versus planned for each team and for the ART overall. Target Range: Ideally, between 80–100% to balance predictability with adaptability.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago